I have argued that criticism of Adani’s Tarali pumped-storage project confuses preliminary survey and site-investigation costs with the full project cost. These are my claims and political interpretations as expressed in separate posts, not independent verification. My project-cost rebuttals connect to adani allegations and investigations and adani power sector projects.
I said the allegation was that Adani deliberately slashed the Tarali project cost from ₹5,675 Cr to ₹56.75 Cr; 5% (₹227 Cr) to avoid depositing it for wildlife conservation.
I said the ₹56.75 Cr figure in the online proposal was only for preliminary site surveys (~1% of project cost).
I said the State Board for Wildlife had already considered the full project cost at ₹5,675 Cr.
I said the project is on private, non-forest land, 3.2 km from Koyna sanctuary, outside the Sahyadri Tiger Reserve buffer and any Eco-Sensitive Zone.
I said no diversion of protected forest or wildlife areas is involved.
I said the explanation was: Propaganda Express mixed up the site-investigation cost with the total project cost.
I said: ₹56.75 crore was exactly what was estimated for preliminary surveys and site investigations; this is not the revised actual project cost; 99% cost reduction is a deliberate lie.
I said the proposed Tarali project had a 1,500 MW capacity is really important to support Maharashtra’s power requirements as renewable energy grows.
I described the sequence as: fake media report via some ecosystem jouurnalist; Congress picks it and target Adani group; Congress IT cell amplify it; psychological warfare to manipulate opinion of public about Modi govt.
I said the approvals before construction were: No-forest-land certificate (Jan 2024); Environmental Clearance (Feb 2025); pollution board consent (Apr 2025).
I said wildlife clearance for survey work was still under National Board for Wildlife review.